Toggle menu

Maybole Community Campus

Maybole Community Campus is set to open at the start of the school year in August 2023. It will incorporate Carrick Academy, St Cuthbert's Primary School, and the new Culzean Primary School and Early Years Centre (formed from the amalgamation of Gardenrose and Cairn Primary schools) creating an inspiring learning environment for up to 1,370 pupils.

The project which will cost approximately £60 million will also feature new outdoor sports facilities, changing pavilion and a new indoor swimming pool which will be available for public use, and a replacement for Maybole Police Station.

The Campus is being built by Morgan Sindall Construction for hub South West Scotland, development partner of South Ayrshire Council.

 

 

Updates

April 2023

The building is wind and watertight and the internal spaces are taking shape. The first of the all-weather sports pitches, sports pavilion and police office have been completed and are in use. The new schools and Early Years Centre are due to open in August 2023 and the swimming pool, which will be available to the public, will open in October 2023, the town's current swimming pool remaining in use until then.

February 2022

Clare Haughey MSP, Minister for Children and Young People visits the construction site.

September 2021

Work starts on the main school campus.

February 2021

Work starts on the first of two new all-weather pitches.

The campus will feature inspiring learning environments as well as top end sports facilities. Attached are images of the new campus

Floor plansLatest images 
Floor plan 1 (PDF) [793KB]
 
Floor plan 2 (PDF) [1005KB]
 
Floor plan 3 (PDF) [949KB]
 
Floor plan 4 (PDF) [630KB]   
Exterior plan 5 (PDF) [911KB]   

Planned layout