Construction Consent
Place and Date of Application
An application for Construction Consent should be made on form CC1
Completed application forms should be submitted at least three months prior to the
intended commencement of construction to the Roads Authority's Representative appropriate
to the locality of the development.
The application for Construction Consent for as large an area as is feasible is
to be recommended. This will allow a roads layout to be established.
The Consent area may be phased and the value of the
Road Bond will be relative to each phase. However, each section must be
able to provide for turning traffic within the section.